• No results found

A numerical study of a catamaran installation vessel for installing

offshore wind turbines

Zhiyu Jiang January 18, 2018 Postdoctoral researcher

Department of Marine Technology

Centre for Marine Operations in Virtual Environments (SFI MOVE) Norwegian University of Science and Technology

2

Outline

1. Introduction

2. The catamaran installation concept 3. Numerical simulation

4. Conclusion

3

Outline

1. Introduction

2. The catamaran installation concept 3. Numerical simulation

4. Conclusion

4

Bottom-fixed Floating

Water depth:

<20m<40m 50-70m >50-100m

Background

5

Capital expenditure of offshore wind

C. Mone et al. (2015) 2015 Cost of Wind Energy Review, NREL

6

Tripod installation using a jack-up vessel (http://worldmartimenews.com)

Jacket installation using a floating vessel (https://www.boskalis.com)

Installation methods - foundation

Monopile installation (www.seawayheavylifting.com.cy)

7

Installation methods - rotor blade

Full rotor Dong Energy Bunny ear

Vatenfall

Single-blade installation Fred Olsen Wind Carrier

8

Installation methods - full assembly

Saipem 7000 Statoil AS

Novel installation vessel Ullstein AS

9

Purpose of numerical simulation

• Design and testing of novel installation methods

• Response-based prediction of limiting operational conditions

• Online decision support for offshore installations

10

Outline

1. Introduction

2. The catamaran installation concept

3. Numerical simulation 4.Conclusion

11

The catamaran installation concept

L.I. Hatledal et al. (2017)

12

Challenges of the concept

• Hydrodynamics

hydrodynamic coupling, sloshing, viscous effect

• Structural dynamics

coupled motion modes, mechanical coupling

• Automatic control

station keeping of the vessel, active ballast system motion tolerance and control, landing force control

13

Installation procedure

14

Monitoring the relative motions

Mating point

15

Properties of the catamaran

16

Properties of the spar

17

Outline

1. Introduction

2. The catamaran installation concept 3. Numerical simulation

Time-domain simulation Frequency-domain simulation

4. Conclusion

18

Time-domain simulation

WADAM: Hydrodynamic analysis of the two-body system

HAWC2: Calculation of the wind forces on the turbine assemblies

SIMO: Time-domain coupled analysis

Catamaran with dynamic positioning system; spar with mooring lines;

sliding grippers between catamaran and spar

19

Modelling of the hydrodynamics

20

Modelling of the sliding grippers

21

Modelling of the mooring system

22

Frequency-domain approach

1. Hydrodynamic analysis of the two-body system

2. Short-term motion prediction of the mating point by using Response Amplitude Operators

23

Magnitude of the pitch RAOs

Spar Catamaran

24

Environmental conditions

Hs=2.0 m Tp Vȕ GHJ

25

Results - relative surge motion

2 m OK 2

Hs Pȕ GHJ

26

Results - relative roll motion

Hs=2.0 m, ȕ deg

27

Conclusion

• A numerical modelling approach of the catamaran installation concept is introduced.

• Future work is needed for implementing the active heave compensator,

dimensioning of the catamaran, active ballast system, etc.

28

Acknowledgements

• Zhen Gao

• Karl Henning Halse

• Peter Christian Sandvik

• Zhengru Ren

Instrumenting the Gravity base foundations for the Blyth Offshore Demonstration wind farm

January 2018 Jonathan Hughes and Paul McKeever

ore.catapult.org.uk

@orecatapult

Agenda

ORE Catapult

Demowind and the FSFound Project

The Blyth Offshore Demonstration Wind Farm

The Project

Instrumentation in the Marine Environment

Future Work

ore.catapult.org.uk

@orecatapult

The catapult network:

A long-term vision for innovation & growth

Catapults

Established by InnovateUK

Designed to transform the UK's capability for innovation

Core grant leveraged with industry and other public funding

11

ore.catapult.org.uk

@orecatapult

ORE Catapult Our Vision:

Abundant, affordable energy from offshore wind, wave and tide

Reduce the cost of offshore renewable energy

Deliver UK economic benefit

Engineering and research experts with deep sector knowledge

Independent and trusted partner

Work with industry and academia to commercialise new technologies

80+ technical experts

ore.catapult.org.uk

@orecatapult

ORE Catapult Business Model

ore.catapult.org.uk

@orecatapult

5x 8.3MW turbines

6.5km off the coast of Blyth

191.5m Tip Height (AOD)

Approx 40m Water Depth

Blyth Offshore Demonstrator Wind farm

ore.catapult.org.uk

@orecatapult

Installation of GBFs at Blyth – Satellite Imagery

NOAH Met Mast 6

7

Image from Aeronet-OC Project

ore.catapult.org.uk

@orecatapult

To validate the FS GBF solution as an alternative solution to energy provision by proving that FS GBF performs as intended and can be installed cost-effectively;

To conduct a range of simulation and modelling studies to minimise the uncertainties and inefficiencies in the deployment process and in various weather windows;

To compare the actual costs and performance with the cost-benefit analysis performed;

To assess structural response to extreme and fatigue loads on the FS GBF and compare theoretical loads with real ones;

To establish the effect of cyclic loadings on the seabed through monitoring and measurement and verify/calibrate models for differential settlements in the soil;

To establish the optimal seabed preparation requirements (i.e. minimum preparation depth).

FSFound Project Aims

ore.catapult.org.uk

@orecatapult

1. Validation of the design, including input to verifying simulation models 2. Providing feedback to the design limits of the structure, such that an updated

life expectancy can be calculated (if required) 3. Understanding the interaction between:

GBF and Seabed (e.g. settlement)

GBF and WTG (e.g. modal interaction, load transfer) GBF/WTG combination and the Environment (e.g. wind/wave misalignment loads)

Effect of internal divisions on the displacement of the caisson outer walls 4. Provide inputs to the design of a Structural Health Monitoring system for GBF

system

5. Provide inputs to the cost model, in the form of estimated O&M OPEX costs 6. Provide a platform for the development of a prognostic methodology for

NDT of GBFs

Aims of the measurement campaign?

ore.catapult.org.uk

@orecatapult

ore.catapult.org.uk

@orecatapult

Caisson Pressure Sensors

Upper sensor mounted near vent (sea reference)

Lower sensor mounted near top of slipform

3 sets of 2 mounted at 120˚ spacing

4Hz sample rate

Upper Pressure Sensor

& Electronics JB

Lower Pressure Sensor Vent Hatch

Wet Joint Indirect measurement of depth

Also can calculate period

Triangulation may permit direction measurement

Comparison after calculation with other wave data on site.

Data corrected for Atmospheric variation

ore.catapult.org.uk

@orecatapult

High stability servo inclinometers

Measurement range of +/-14.5˚

Resolution of 0.001˚

Positioned to match ANSYS AQWA modelling nodes

Positioning is critical to interpretation of data

Inclination and Mode Shapes

Inclinometer

ore.catapult.org.uk

@orecatapult

Initially aimed to installed SGs into Concrete, however not possible

Structure can be analysed through load paths rather than direct loads

Bending, Compression and Torsion are independently assessed

Loads measured above and below “Wet Joint” – calculation of loads into caisson roof

Loads measured at field weld to establish effect of loads from turbine and torsional loads

Load Paths

Strain Gauges (Below Wet Joint)

Strain Gauges (Above Wet Joint)

Strain Gauges (Above Wet Joint)

ore.catapult.org.uk

@orecatapult

Structures are filled ballasted with sand and seawater flooded below LAT

Water is expected to have slow transit rate through structure, leading to oxygen depletion

Dissolved Oxygen sensors are installed to monitor

Water level in shaft is monitored for comparison

DO Sensors use dynamic luminescence quenching rather than an EC sensor

Corrosion

From AADI 4330 manual

ore.catapult.org.uk

@orecatapult

Instruments are useless if they don’t work or give questionable data

Welding and Bolting were not permitted by the designer

All instruments are permanently bonded, but need a temporary method of attachment until the adhesive “grabs”

Protection needed against ballasting force

Protection against settlement

Subsea-grade cables and connectors

Full epoxy fill to instrumentation systems

Connection and Protection

ore.catapult.org.uk

@orecatapult

Vertical installation requires significant additional time and risk management

Installing delicate sensors; to fine tolerances; in the wet; hanging from a rope…

Horizontal installation challenging without the ability to roll or traverse

Installation Challenges

Location Referencing

Novel and Evolving design

Fitting research into a complex and time-critical construction project

ore.catapult.org.uk

@orecatapult

How close are models to their physical counterparts?

Pipe B

Pipe A

Brackets Sensor Axis

CP String A

Pipe C

Pipe D Pipe E CP String B

CP String C

CP String D

CP String E Pipe F Hardware Driver

Created

VOB Server OPC Connection Software Unit Test

Unit to Main Integration

Core Main Software (Logging and Communication)

Software Unit Test

Server-side software for OPC

Software Unit Test

Software

Cabling Verification, Interconnects

Hardware Acceptance Test

Encapsulation

Installation into Foundation

Site Acceptance

Test Replication of PC for

Backup

Test ODSL File Server

ore.catapult.org.uk

@orecatapult

Example Data – Inclinometer Profile

ore.catapult.org.uk

@orecatapult

Planning for Analysis

Flowcharts convert theory into algorithm for processing

ore.catapult.org.uk

@orecatapult

Commercial Ideals

Strong “proven” technical solution

Warrantable performance allowing for “tight” contracts

No unexpected outcomes Research Ideals

Cutting Edge “novel” technical solution

Project technical output comes before programme

Unexpected outcomes are interesting (isn’t that why we do it?)

The best common outcomes only come through

Close collaboration between practical and theoretical work

Novel techniques but proven technologies and strong theoretical base

Trial and error (more trials, fewer errors!)

Why is Research in a Commercial Project so challenging?

Ballast Pipe

Test Rod (same dimension as widest part of plug)

Pipe Aperture

Shaft

ore.catapult.org.uk

@orecatapult

BLYTH ORE Catapult National Renewable Energy Centre Offshore House Albert Street Blyth, Northumberland NE24 1LZ

T +44 (0)1670 359 555 F +44 (0)1670 359 666 GLASGOW

ORE Catapult Inovo

121 George Street Glasgow G1 1RD

T +44 (0)333 004 1400 F +44 (0)333 004 1399

LEVENMOUTH ORE Catapult Fife Renewables Innovation Centre (FRIC) Ajax Way

Leven KY8 3RS

T +44 (0)1670 359 555 F +44 (0)1670 359 666

info@ore.catapult.org.uk ore.catapult.org.uk

Contact us

Integrated design optimization of jackets and foundations for offshore wind turbines

Kasper Sandal Chiara Latini Varvara Zania Mathias Stolpe

1

ABYSS– Advancing BeYond Shallow waterS funded by Innovation Fund Denmark

DTU Wind Energy, Technical University of Denmark 06 October 2017

This is how optimization can become a valuable tool for structural engineers in offshore wind

minimize ݂(࢞) subject to ࡭࢞ െ ࢈ ൑ ૙

࣌ ൑ ࣌ ࢞ ൑ ࣌

࣓ ൑ ࣓ ࢞ ൑ ࣓

Design considerations Optimal design problem

Design trends

2

DTU Wind Energy, Technical University of Denmark 06 October 2017

This is how optimization can become a valuable tool for structural engineers in offshore wind

minimize ݂(࢞) subject to ࡭࢞ െ ࢈ ൑ ૙

࣌ ൑ ࣌ ࢞ ൑ ࣌

࣓ ൑ ࣓ ࢞ ൑ ࣓

Design considerations Optimal design problem

Design trends

3

minimize ݂(࢞) subject to ࡭࢞ െ ࢈ ൑ ૙

࣌ ൑ ࣌ ࢞ ൑ ࣌

Design considerations Optimal design problem

Design trends

࣌ ൑࣌ ࢞ ൑

࣓ ࢞

DTU Wind Energy, Technical University of Denmark 06 October 2017

minimize ݂(࢞) subject to ࢍ ࢞ ൑ ૙

Objective function

How to formulate a numerical optimization problem:

Let xbe a vector of variables, where we want to minimize f(x)

4

Constraint functions

DTU Wind Energy, Technical University of Denmark 06 October 2017

minimize ݂(࢞) subject to ࢍ ࢞ ൑ ૙

= design variables:

1. Diameters &

wall thickness 2. Diameters, wall

thickness, &

length ŽƐƚу:ĂĐŬĞƚнĨŽƵŶĚĂƚŝŽŶŵĂƐƐ

Engineering limits:

1. Fatigue limit state 2. Ultimate limit state 3. Soft-stiff frequency range

How to design a jacket and its foundation with optimization:

Let xdescribe the design, f(x) the cost, and g(x) the engineering limits

5

DTU Wind Energy, Technical University of Denmark 06 October 2017

minimize ݂(࢞) subject to ࢍ ࢞ ൑ ૙

The optimization problem has very few design variables, but a high number of nonlinear constraints

6

o 24 design variables for the jacket o 3 design variables for the foundation o 7k constraints for each static load

¾Stress along all tubular welds

¾Shell buckling & column buckling

¾Foundation capacity o 2 frequency constraints

DTU Wind Energy, Technical University of Denmark 06 October 2017

:KW

Mesh Loads Finite Element

ŶĂůLJƐŝƐ Sensitivity

analysis WŽƐƚ

processing Interfacing scripts

fmincon ' /WKWd W>y Built-in solvers

The problem is implemented in the special purpose software JADOP (Jacket Design Optimization)

7

DTU Wind Energy, Technical University of Denmark 06 October 2017

We make assumptions in the structural analysis which are suitable for the conceptual design phase

8

o Timoshenko beam elements for the support structure

o Linear 6-dof responsefor each foundation o 4 Damage equivalent loads for the fatigue limit state o 3 Extreme static loads for the ultimate limit state o Conservative analysis of column buckling o Stress concentration factors in welded tubular joints No safety factors are applied in the following examples

DTU Wind Energy, Technical University of Denmark 06 October 2017

For a given design problem (10 MW turbine, 50 m depth, piles), the total mass was minimized to 631 tons (in 5 minutes on a laptop)

9

Piles in sand Diameter: 1.41 m

Length: 50 m

Mass: 140 tons

Jacket

Mass: 491 tons

Soil: Medium stiff sand

Foundation: Wiles Design procedure: W/

32 m

DTU Wind Energy, Technical University of Denmark 06 October 2017

JADOP has a parameterized mesh which makes it a quick task to modify for example the leg distance

10

DTU Wind Energy, Technical University of Denmark 06 October 2017

When support structures with different leg distance are optimized, jacket mass and foundation mass show opposite design trends

11

Medium stiff sand

DTU Wind Energy, Technical University of Denmark 06 October 2017

The optimal leg distance will depend on for example the soil stiffness

12

Medium stiff sand

DTU Wind Energy, Technical University of Denmark 12

Very stiff sand

DTU Wind Energy, Technical University of Denmark 06 October 2017

But several other aspects of the anchoring will also influence the design problem

We have looked at:

WŝůĞƐΘƐƵĐƚŝŽŶĐĂŝƐƐŽŶƐ

Sand & clay

Varying soil stiffness

Different design procedures for piles

13

Source: SPT Offshore

Suction caisson

Source: 4coffshore

WŝůĞƐ

DTU Wind Energy, Technical University of Denmark 06 October 2017

The design considerations are “translated” into an optimization problem, and it is now a quick task to generate design trends

minimize ݂(࢞) subject to ࡭࢞ െ ࢈ ൑ ૙

࣌ ൑ ࣌ ࢞ ൑ ࣌

࣓ ൑ ࣓ ࢞ ൑ ࣓

Design considerations Optimal design problem

Design trends

14

DTU Wind Energy, Technical University of Denmark 06 October 2017

The figure below shows how jacket mass and foundation mass change as functions of both leg distance and soil stiffness (A=stiff, D=soft)

xº F

Fz

ªux

uz

15

Soil = sand

Foundation = piles

DTU Wind Energy, Technical University of Denmark 06 October 2017

The preferred leg distance now depends on the soil stiffness, and perhaps also the desired fundamental frequency

º Fx

Fz

ªux

uz

16

Soil = sand

Foundation = piles

DTU Wind Energy, Technical University of Denmark 06 October 2017

Structural optimization is used to automate the “well-defined”

engineering tasks of conceptual support structure design

17

= design variables Cost function

Engineering limits:

1. Fatigue limit state 2. Ultimate limit state 3. Soft-stiff frequency range

minimize ݂(࢞) subject to ࢍ ࢞ ൑ ૙

DTU Wind Energy, Technical University of Denmark 06 October 2017

With a tool like JADOP it is then quick & easy to investigate how input conditions influences the design

18

minimize ݂(࢞) subject to ࢍ ࢞ ൑ ૙

F) Wind farm optimization

The DIMSELO Project (Dimensioning Sea Loads for Offshore Wind Turbines), F. Pierella, IFE

A savings procedure based construction heuristic for the offshore wind inter-array cable layout optimization problem, S. Fotedar, University of Bergen

Calibration and Initial Validation of FAST.Farm Against SOWFA, J.Jonkman, National Renewable Energy Laboratory

An Experimental Study on the Far Wake Development behind a Yawed Wind turbine, F. Mühle, NMBU