• No results found

Updates on Project Governance Research

N/A
N/A
Protected

Academic year: 2022

Share "Updates on Project Governance Research"

Copied!
29
0
0

Laster.... (Se fulltekst nå)

Fulltekst

(1)

Concept Symposium 2018

Governing Megaprojects – Why, What and How

Updates on Governance Research in Norway

Knut Samset

Program Director, Professor Concept Research Program, NTNU Norway

The Concept research program was established in 2002, to develop knowledge and expertise to ensure efficient use of resources and enhance the benefits of major public investments. The focus is on project governance, and the long term benefits of investments, as seen from the financing party’s perspective. It is also essentially restricted to the front‐end before the commitment to finance, since this is the period when the most essential decisions are made.

This is a time of urgency, since the possibility to make major changes decreases as projects enter into their planning and implementation phases. What is required is interdisciplinary research, where the social sciences merge with project management and engineering.

Current research is on environmental impact and sustainability, financing mechanisms, governance schemes, investment practices, technological change, ex ante and ex post evaluation, productivity and flexibility.

https://www.ntnu.edu/concept/concept‐symposium

The Concept Symposia on Project Governance

The Norwegian Ministry of Finance and the Concept Research Program hosts every second year a symposium on project Governance. Project governance, in brief, is concerned about investments and their outcome and long‐term effects. In view of the problem at hand, the aim is to ensure that the best conceptual solution is chosen, that resources are used efficiently and anticipated effects realized. Resource persons from ministries, governmental agencies, academia, international organizations, and industry are invited. In order to facilitate professional exchange and direct communication between participants, the number of individuals is restricted. The aim is to initiate further international cooperation and research on important issues related to project governance.

Gro Holst Volden

Research Director

Concept Research Program, NTNU Norway

(2)

Updates on

Project Governance Research

Eighteen years of research

by the Concept Research Program

Gro Holst Volden, Research Director, Concept Knut Samset, Program Director, Concept

(3)

The Concept Research Program

Steering group

Other Norwegian universities and R&D

institutions

NTNU

The Concept Research Program Research team

International research community

Ministry of Finance

consultantsQA

Ministries

Public agencies

The QA scheme

(4)

Economic analysis (37, 38, 39, 41)

Valuing the Future (27)

Foresight methods (53)

Ex ante evaluation (5, 8, 9, 20, 16)

Alternatives analysis (18)

Market competition (31)

Market and environmental policy (24)

Economic viability (22, 48)

Political

science Economic

science Management

science

Pre-project Governance (26)

Environmental impact (48)

Political control/decisions (3, 26, 43)

Governance and governance frameworks (23, 25, 33, 35, 36, 45, 46, 47, 50)

Research on governance of major investment projects

Ex post evaluation (4, 7, 19, 28, 30, 52)

Sustainability (29)

Negative impacts (54) Strategic alignment (6, 21)

Thematic focus on project governance

Uncertainty (1, 10, 11, 12, 13, 14)

Costs (51)

Cost estimation (15)

Design and Decision (26)

Decisions based on scant info. (17)

The opportunity space (34)

Economic incentives (2)

Perverse incentives (40)

Systematic uncertainty (32)

Financing mechanisms (42, 44, 49)

(5)

Idea/

conceptual phase

projectPre-

studyPre- Con-

struction

Commis- sioning and

operation

Front-end governance – Quality at Entry to ensure project success

Relevance Commitment

Interests IncentivesCost Obligations

Objectives Strategy

Opportunity space Concepts

Alternatives analysis Estimation

Real options

Cost Timing

Scope Contracts Responsibilities

Budget

Timing Relevance

Benefit/cost Output Outcome

Impact Sustainablilty

Double-loop learning

Detailed

engineering Evaluation

(6)

Idea/

conceptual phase

projectPre-

studyPre- Con-

struction

Commis- sioning and

operation Detailed

engineering

The Norwegian «State Project Model»

BudgetQA2

Parliament decision

Political appraisal or decision Technical assessement or Quality assurance ConceptQA1

Government decision

A simple two-gateway procedure

(7)

Our main concern is the quality of

analysis. But the final outcome depends as much or more on political decisions

• The road to success is paved with stumbling stones

• The chance of success is reduced accordingly:

Success

Restriced failure Failure

Failure

Success

Restricted failure Failure

Complete failure

Outcome

Implemen- tation

Initial idea

Right Wrong

Decision process

Analysis and decision – the road to success

Per cent right/wrong > Chance of success

20/80 4

50/50 25

80/20 64

(8)

“Over budget, over time, over and over again.”

The “iron law of megaprojects” (Flyvbjerg)

The “established” truth:

70 per cent above budget

Results from the Norwegian scheme so far

N = 84

Concept report no. 51

Norwegian QA projects:

70 per cent under budget

(9)

Efficiency Effectiveness Impact Relevance Sustainability Cost-benefit efficiency

Score 5-6 Score 3-4 Score 1-2

N = 20

Concept report no. 52

Results from the Norwegian scheme so far

Ex post evaluation average score:

• Operational success 4.7

• Tactical success 4.7

• Startegic success 4.5

• Benefit/cost 4.2

(10)

Quality assurance

1 Billion NOK

Outcome Savings and economic benefits

15+ Billion NOK Input

300+ billion NOK

Research (Concept)

0,01 Billion NOK

Quality at Entry (QaE) and Front-end Research

Benefit/cost ratio:

Quality assurance 15Bn/1Bn = 15

Research 15/0.01= 1500

The transistor analogy

(11)

Research topics

(12)

Political appraisal or decision Technical assessement or Quality assurance

Norway Denmark Sweden

The Netherlands Canada (Quebec) Great Britain

Concept report no. 47

Governance schemes in different countries

Similarities and differences

FagMinistries FagMinistries Parliament

EtatEtat

Regional authorities

Agencies Ministry of

Finance Other

ministries Cabinet

QA

FagMinist ries FagMinistrie

s Parliament

EtatEtat Agencies Ministry of

Finance

Ministry of Transport QA

Cabinet Cabinet office

Regional authorities

Etat FagMinistries FagMinistries Parliament

AgencyEtat Ministry of

Finance Other

ministries Cabinet

Internal QA Cabinet office

Regional authorities

FagMinistries FagMinistries Parliament

Cabinet

EtatEtat

Regional authorities Ministry of

Finance

Ministry. of Infrastructure and Environment

Agencies/

industry ICRE

CPB/

PBL

FagMinistries FagMinistries Provincial

Parliament

EtatEtat

Regional government

Agencies Treasury

Board Ministries

Council of ministers

SQI .

FagMinistries FagMinistries Parliament

EtatEtat

Counties

Government agencies

HM Treasury Other

ministries IPA

Government Cabinet

office

(13)

Political appraisal or decision Technical assessement or Quality assurance Final approval and budget

Norway

Sweden Denmark

The Netherlands

Great Britain Canada (Quebec)

Denmark Idea

phase Pre-project Detailed

engineering

Pre-study Construction Commissioning

and operation

Phase 1 Preliminary investigations

Phase 3 Detailed engineering

Phase 4 Tendering and commissioning Phase 2

Decision basis

Intern Intern Intern Conceptual

appraisal Strategic/operational plan Detailed

engineering and production

Commissioning and operation

Phase 5 Construction and

operation

Concept report no. 47

Governance schemes in different countries

Planning/

development Realization phase Exploration phase

Idea phase

1. The Front-end

phase 3. The Plannig

phase 4- The Execution

phase 2. The Initiating

phase 5. The closing

phase

Policy

formulation IAAP Delivering the Operations

project (design/build/test) Project initiation

Strategic

OutlineCase Outline

Business Case Full Business Case

(14)

Improved governance measures at lower levels in public administration

• Agencies have introduced their own project models

• Clearly defined phases, decision points, roles, responsibilities, and quality assurance

• Consistent with the State Project Model

• Ministries follow up projects in subordinate agencies “as needed”, often informally

Concept report no. 50

Dispersion of the QA scheme

(15)

QA schemes are also introduced at the municipal level in Norway.

Also for smaller and more standardized projects, but where cost overrun is are common.

Considerable variation in terms of terminology, roles, focus areas etc.

Concept report no. 45

Improved governance measures at lower levels in public administration

Expanse of the QA scheme

(16)

Analysis and decision

• The term “opportunity space” rarely used

• Lack of balance between the overall societal and the

detailed project-specific

• Path dependency in more than half of the projects

Predetermined solution: 90 %

New problems introduced later 30%

Conceptual solution different from the

initial: 40 % Conceptual solution

same as the initial 60%

Unambiguous needs analysis:

50 %

No predetermined solution: 10 %

Concept report no. 26

The problem of path dependency

(17)

• There is considerable room for improvement, even in projects that have undergone QA1

• The challenge is to keep the opportunity space open

• External QA helps to weed out the worst conceptual alternatives

• Sound analyses may be overruled by political priorities

Concept report no. 34

Analysis and decision

The opportunity space is restricted

(18)

Final budgets are now largely realistic.

The earliest cost estimate may be severely underestimated

Front-end cost escalation

Concept report no. 39

10%0%

20%30%

40%50%

60%70%

80%90%

100%

This may allow for inferior project ideas

Which are subsequently approved and implemented

(19)

Test case: The design-to-cost approach has been applied with success.

The National Police Response Centre project

Working paper 2018

Front-end cost escalation

QA1 QA2 Final

cost Average QA projects

increase between QA1 and QA2

NNPRC Cost change

(percentage)

+ 40 %

-15 % 100 %

?

(20)

• Cost performance in Norwegian QA projects is acceptable on project level

• More variation on contract level.

• Expensive change orders is not uncommon.

• A source of conflicts and delays.

• Ongoing study tries to explain what causes cost overruns on contract level

Ongoing study

Cost management in construction contracts

26%

74%

Underruns Overruns

(21)

The cost-benefit analysis

• The conclusions from CBA is not being used (not trusted?)

• Black box analyses / lack of transparency

• Susceptible to optimism bias -> Could be avoided by quality assurance

• Inadequate treatment of non-monetary impacts

Stad shipping tunnel – an extreme case of inconsistent analyses

Concept report no. 33, 37, 38, 40

Some challenges and weaknesses

(22)

Neglected and underestimated impacts of transport projects

• Wider economic benefits

• Non-financial costs during construction

• Induced traffic and urban sprawl

• Underpricing of the environment

Concept report no. 54

The cost-benefit analysis

(23)

• Essential underlying principles and trends in technology and societal change

• Market and user responses

• The use of simulation models to predict

“extreme scenarios”

• Foresight methods that may supplement quantitative prediction methods.

• Uncertainties and risk to be incorporated in such analyses.

Trends and paradigm shifts in the age of disruption

Concept report no. 41, 53

Conceptual solutions in forthcoming long-term projects

(24)

• Probability distributions and uncertainty intervals are clearly defined, but understood?

• Further about non-experts’ understanding of

probability: principles, terminology and distributions.

• Accuracy in use quantitative and qualitative measures of probability

• The risk of misunderstandings is substantial

• Highly affected by the words that accompany the figures.

Expert assessment about probabilities

P50

True cost, or misconception?

Concept working paper 2018

The extent to which they are understood by

decision-makers and non-experts?

(25)

Ex-post evaluation of projects

A minimum evaluation procedure has been developed and applied

So far on 20 completed projects.

Six criteria that in combination assess their strategic, tactical and operational success.

The approach provides

sufficiently detailed information at the individual project level

A comprehensive overview at portfolio level.

0 1 2 3 4 5

Efficiency6

Effectiveness

Other impacts

Relevance Sustainability

Benefit-Cost efficiency

Project 1 Project 2

Concept report no. 30, 52

(26)

Some research findings

1. The success paradox: Success is measured in terms of tactical performance rather than strategic performance.

2. The paradox of managing uncertainty and risk: Resources are used during implementation, much less up-front.

3. The paradox of early information overflow: Expensive, time consuming and obscuring rather than clarifying

4. The paradox of the unexplored opportunity space: Path dependency rather that innovative thinking

5. The paradox of strategic alignment: Commonly erroneous internal and external logic, and probabilistic assessment

Ten paradoxes regarding project governance and practices

(27)

6. The paradox of cost estimation: Focus is on the detailed budget, must less on realistic estimation up-front.

7. The paradox of decision-makers’ disregard of the CBA: conclusions are commonly overruled by other concerns.

8. The paradox of “predict and provide”: the tendency is to prefer a “predict and provide”

strategy rather than exploring alternative solutions.

9. The paradox of perverse incentives: No financial obligations for the beneficiaries cause perverse incentives an tend to result in counterproductive projects.

10. The paradox of myopic decisions: – long-term viability is the intention, but the planning horizon is short, resulting in choices that will prove inferior in the long run.

Some research findings

Ten paradoxes regarding project governance and practices

(28)

The research team

(29)

www.ntnu.edu/concept

Referanser

RELATERTE DOKUMENTER

This paper explores the initial phase of the N2 Gateway project from 2004 to 2006 as a case study of the politics of urban governance in Cape Town As a centralised and

This Issue paper forms part of a three-year U4 project entitled “REDD Integrity.” Funded by the Norwegian Ministry of Climate and Environment via Norad,

None of the project partners responding to our email survey chose to engage explicitly with the question posed on how they dealt with gender as a concept. Considering the

In this presentation I provide a brief thematic orientation about the project “Making Sense of the Aurora,” a multi-disciplinary Nordic research network based at

The objective of this five-year project (2011-2015) financed by the Norwegian Ministry of Foreign Affairs is to improve food security by making agriculture and livestock production

At the time it was described as the largest public IT investment in Norway, and also the first IT‐project to be subject to the Norwegian scheme for quality assurance of major

Summary: The report provides a description of the Norwegian State Project Model, also referred to as the government’s scheme for external quality assurance of major public